Breaking down the annual cost of a Dubai flat, item by item

District cooling: the fixed charge when a flat is empty

Part of the Empower cooling bill does not depend on use: even if the flat stands empty and the service is temporarily disconnected, the demand charge and the meter fee continue to apply.

Cooling · · updated

750 AED/RTAnnual

In a flat connected to district cooling, the cooling does not come from the building’s own air conditioning but from chilled water supplied by a central plant. What this means for the budget: part of the bill is calculated not on use but on the capacity the flat is connected to, and it accrues even while the flat is empty.

This bill is for the flat’s own cooling. The air conditioning of corridors, the lobby and other common areas is paid for separately, as one of the headings of the service charge.

Two separate charges

On the charges explanation page of Empower, one of the district cooling companies, the items are defined separately. The amounts below come from that general explanation page and should be checked against the project’s contract and bill. Another supplier or a different contract should not be assumed to use the same tariff.

Item How it is calculated
Consumption charge 0.568 AED per refrigeration ton-hour (RT·h), by meter reading, in arrears
Demand charge 750 AED per RT per year, billed in advance, according to the number of days in the month
Meter maintenance 50 AED per quarter or 30 AED per month (depending on location)

The worked example on the page gives the annual demand charge for a 6 RT flat as 6 × 750 = 4,500 AED. The RT here is the flat’s air-conditioning load: the figure comes not from the flat’s area but from the cooling capacity it is connected to, and it does not change even if nobody lives there.

Temporary disconnection does not stop the fixed charge

The same page says that a temporary disconnection at the account holder’s request is a transaction costing 150 AED, after any outstanding balance has been settled. It also makes this distinction:

Demand Charges and Meter Maintenance Fee will be continued to be charged irrespective of the property is disconnected.

Temporary disconnection does not stop the demand charge or the meter fee. Consumption remains tied to the meter record; earlier usage and outstanding balances should not be assumed to disappear. Whether the consumption charge or the fixed charges are larger depends on the flat’s consumption; it cannot be generalised from this page. In a two- or three-month gap while looking for a tenant, the figure to put in the budget is not zero but the share of the demand charge and meter fee falling in those months.

Closing the account completely is a separate process, and the result of a temporary disconnection should not be carried over to it. Empower’s final bill page lists a copy of the new title deed among the documents required from an owner, so the process it describes applies when the property changes hands. If ownership is not changing, the page does not say which process applies; that has to be confirmed with Empower.

Each of the items listed also carries 5 per cent VAT. Empower also says it passes on to customers the tariff increases and fuel surcharge notified by DEWA; the current amount should be taken from the bill or confirmed with the supplier, rather than replaced with an unsupported budget range.

Translated from the Turkish article.

This article is filed under Cooling. The other articles on the same item are listed there.